Error While Closing Project. "Mandatory resources for this activity ... have not been assigned. Assign the resources before completing this activity." Instantis EnterpriseTrack (Doc ID 2188852.1)

Last updated on SEPTEMBER 30, 2016

Applies to:

Instantis EnterpriseTrack Cloud Service - Version 15.1.0.0 and later
Instantis EnterpriseTrack - Version 15.1.0.0 and later
Information in this document applies to any platform.

Symptoms

When attempting to Close a project that has all child activities closed, and only one phase open, the following error occurs:

Error while Closing Project. Please correct the errors shown below, and try again.
 Mandatory resources for this activity have not been assigned. Assign the resources before completing this activity.


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Access the account as a user with permission to Edit and close a project
2. View the Project Schedule
3. Verify all Child activities are closed, and only one phase remains open.
3. Click the Close Project button

Changes

 Possible change is new "Roadmap" has been created.

Cause

Sign In with your My Oracle Support account