Bar Filter Based On Current Date or Data Date Not Applied To Any Activities (Doc ID 2193415.1)

Last updated on OCTOBER 21, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.3 and later
Information in this document applies to any platform.

Symptoms

Bar Filter Based On Current Date or DD Not Applied To Any Activities
 

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a new project.
2. Add two activities. Set the duration to '5d' on both, and link them together with a Finish to Start relationship.
3. Schedule the project.
4. Move the system date so that it is between the finish dates of the two activities.
5. Go to View -> Bars.
6. Add a new bar, set the timescale to 'current bar' and give it a unique color.
7. Move the bar to the bottom of the list.
8. Add the following filter to the bar:
Where Finish IS Less Then or equal to Current Date
9. Save and view bar chart.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms