Planned Order for a Make Item shows the Implement As as 'None' (Doc ID 2193798.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Materials Requirement Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

There exists a problematic  org  in which when an MRP is run, the parent item is getting a planned order recommendation but the Implement As Option is shown as 'None'

It is also found that none of the components / subassemblies of the parent item are getting planned by MRP . Neither does the planned order demand appear for these items nor does the planned order appear for these component items.

Cause