When Inserting Activity on the Gantt Chart Using Edit > Insert > Activity, Start Date Defaults to Today's Date Instead of Parent's Start Date (Doc ID 2194805.1)

Last updated on AUGUST 08, 2017

Applies to:

Oracle Agile Product Portfolio Management - Version 9.3.4.0 and later
Information in this document applies to any platform.

Symptoms

Actual Behavior

Activity Default Date defaults to today's date and ignores parent relationship while adding activity from Edit menu on the Gantt Chart

Expected Behavior

Activity Default Date to match the parent relationship while adding activity from Edit menu on the Gantt Chart

Steps to Reproduce

1. Login to Web Client, and open a Project which started in the past date (i.e. Project Start Date is Oct 1, and today is Oct 19)
2. Goto Schedule tab, and launch Gantt Chart
3. Select the Activity under phase. Phase has started in the past date (i.e. Oct 1)
4. Click on Edit > Insert > Activity. See the start date is today's date (i.e. Oct 19) instead of pointing to the Start Date of the parent (in this case, Phase) (i.e. Oct 1)

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms