Goal

On : 12.2.3 version, Install/Configuration

Stop Inline Forecast Consumption on Demantra Forecast in ASCP Plan

Plan options are set in such a way that it plans for both Forecast and Sales orders.
Sales orders should be part of the demand picture, but Sales Orders should not consume the Forecast.

Demantra is used to generate forecast and is fed into the ASCP plan for each organization as Demand schedule.

Question : Is there a way to stop Forecast Consumption in ASCP Plan?

Solution