Costs Not Displayed in Report for Closed Projects (Doc ID 2197668.1)

Last updated on NOVEMBER 01, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.2.0.0 to 15.2.11.0 [Release 15.2]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.2.0.0 to 15.2.11.0 [Release 15.2]
Primavera P6 Professional Project Management - Version 15.2.0.0 to 15.2.11.0 [Release 15.2]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
When running a report to view time distributed data by month for Period At Completion Total Cost at the Project/EPS level for closed projects, no data is displayed.

EXPECTED BEHAVIOR
-----------------------
Expect Period at Completion Total Cost to be shown for closed projects.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Log into P6 Pro and verify User Preferences setting set to view "All Closed Projects" under Resource Analysis. Also, ensure summary data exists for projects being reported on.
2. Run report showing time distributed data for Period at Completion Total Cost at the Project level.
3. Notice no costs appearing in the report for the given timescale.
4. Open a project with period costs for the report timescale.
5. Rerun report.
6. Note that Period at Completion Total Cost is now showing as expected.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms