"Sent to Schedule Sheet" Fails With "Quantity (Qty): Cannot be zero for resource xxx".

(Doc ID 2199239.1)

Last updated on DECEMBER 09, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version and later
Information in this document applies to any platform.


When clicking "Send to Schedule Sheet" in P6 Web, it fails with following error:

Error: Import of Schedule activities failed reason : Error occurred :
Quantity (Qty): Cannot be zero for resource xxx on activity xxx.

The issue can be reproduced at will with the following steps:
1. Login P6 Web
2. Choose one project, run Sent to Schedule Sheet
3. Check the job and find it is failed with 0 quantity error.