The Reconcile Process Should Update the Activity Column of Affected Circuits in the Conn Design Search and Connection Summary Windows (Doc ID 2201044.1)

Last updated on NOVEMBER 04, 2016

Applies to:

Oracle Communications MetaSolv Solution - Version 6.2.1 and later
Information in this document applies to any platform.

Goal

REQUEST REQUIREMENT

Request Reconcile be noted in the Activity field of a circuit that has had a cascading reconcile affecting the circuit
Talked with Product Mgmt about this request in a management call.

JUSTIFICATION

Reconcile process should update the Activity field for the affected circuits, as this happens outside of the user's control and needs to be documented.

The following mock up picture shows the Reconcile in the Activity columns

 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a