Symptoms

Published data based on baseline data not updated in extended schema after change in project baseline assignment.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. In project preferences set Earned Value to 'Project Baseline'
  2. Create a test project with two activities
  3. Assign baseline as current project
  4. Publish the project
  5. Create a baseline from the current project and assign as project baseline. Planned Value still 0 (which is correct)
  6. Publish the project. The "Planned Value" is now greater than 0 hours
  7. Re-set the Baseline to “Current Project". This resets the Planned Value to 0 in the project
  8. After publishing the project again, the Earned Value data in the extended tables for the activities are not changed

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms