Start Dates of the Forecast Curve Are Pulled Back if There Are No Actuals

(Doc ID 2208181.1)

Last updated on NOVEMBER 28, 2016

Applies to:

Primavera Unifier Cloud Service - Version 15.2.0.0 to 15.2.0.0 [Release 15.2]
Primavera Unifier - Version 15.2.0.0 to 15.2.0.0 [Release 15.2]
Information in this document applies to any platform.

Symptoms

On Unifier : version 15.2.11.2

Expected Result: Forecast type Cash Flow curves that are configured to use the Schedule Sheet for start/finish dates should be using the dates from the Schedule Sheet

Actual Result: Forecast type Cash Flow curves that are configured to use the Schedule Sheet for start/finish dates are not using the dates from the Schedule Sheet

Cause