When Updating Remaining Labor Units Using The API The Value Does Not Change if The Value is Less Than a Difference of 0.50. (Doc ID 2210112.1)

Last updated on DECEMBER 08, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.2.4.0 and later
Information in this document applies to any platform.

Symptoms

When attempting to update the remaining labor units with a value less than .50, the value will not change in P6 EPPM.

For example:

- When updating the value from 10.00 to 10.40 using the API, the displayed value is 10.00.
- When updating the value from 10.00 to 10.50 using the API, the displayed value is 10.50.

Cause