My Oracle Support Banner

ASCP Not Suggesting Rescheduling For Buy Items Based On Dock Dates (Doc ID 2210718.1)

Last updated on OCTOBER 19, 2019

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.5 version, Data Collections

ACTUAL BEHAVIOR
---------------
In the Supply Chain Workbench, there is a PO for item 102W1291P001. This PO has an Old Dock Date of 11-NOV-2016 and a Sugg Dock Date of 14-NOV-2016, but the Action for this PO is None.

EXPECTED BEHAVIOR
-----------------------
11-NOV-2016 is a non-working day, so the Action for the PO should be to Reschedule Out.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run plan



Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.