EBS: PS: Related Operations associated with a Work Order are not highlighted when selecting any Operation within Resource Gantt (Doc ID 2211504.1)

Last updated on JANUARY 29, 2017

Applies to:

Oracle Production Scheduling - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Within latest patch of EBS 12.1.3/VCP 12.1.3.9.1 Version (PS 12.1.3.8C649 - Patch 22782885:R12.MSC.B); Related Operations associated with a Work Order are not highlighted when selecting any Operation within Resource Gantt. However, if any intermediate Operation is selected it highlights all the related Operations. Issue is random and does not happen across all the Work Orders.

Cause

Sign In with your My Oracle Support account