Agile 9.3.5 - Delegate Owner From Gantt Does Not Add Activity Owner To The Team Tab (Doc ID 2215103.1)

Last updated on AUGUST 08, 2017

Applies to:

Oracle Agile Product Portfolio Management - Version 9.3.5.0 and later
Information in this document applies to any platform.

Symptoms

On : 9.3.5.0 version, Gantt Chart

ACTUAL BEHAVIOR
---------------

When delegate owner of a task or phase in Gantt Chart, the task ownership is updated but the activity owner name is not added to the team tab of the activity they owned.
Steps:
1) Edit a project using Gantt
2) in Gantt, change task owner
3) Save and open the task in Agile
3) the owner is updated with the new name but in the team tab, the new name is not added.


Cause

Sign In with your My Oracle Support account