Symptoms

On : 12.1.3 version, APS Feedback

ACTUAL BEHAVIOR
---------------
After releasing Plan order from ASCP, the dates in the batch - start and end dates for some batches are not in sync with planned order

EXPECTED BEHAVIOR
-----------------------
Planned order dates should match the batches created

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. (R) Advanced Supply Chain Planner
2. (N) Supply Chain Plan / Names
3. Query the Plan and click launch
4. Wait for plan run to complete
5. (N) Supply Chain Plan / Workbench
6. Release planned order

Issue is happening for random orders and not consistently reproducible


Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms