My Oracle Support Banner

Batch Start and End Dates for some Batches are Not in Sync with ASCP ECC Plan Recommended Date (Doc ID 2218420.1)

Last updated on JUNE 27, 2018

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Oracle Process Manufacturing Process Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, APS Feedback

ACTUAL BEHAVIOR
---------------
After releasing Plan order from ASCP, the dates in the batch - start and end dates for some batches are not in sync with planned order

EXPECTED BEHAVIOR
-----------------------
Planned order dates should match the batches created

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. (R) Advanced Supply Chain Planner
2. (N) Supply Chain Plan / Names
3. Query the Plan and click launch
4. Wait for plan run to complete
5. (N) Supply Chain Plan / Workbench
6. Release planned order

Issue is happening for random orders and not consistently reproducible


Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution