Broken Pegging And Negative PAB In Constraint Without Details Scheduling Plan (Doc ID 2218566.1)

Last updated on JANUARY 05, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.5.1 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.5.1 version, Constrained planning

ACTUAL BEHAVIOR
---------------
Broken Pegging and negative Projected Available Balance in Constraint Without Details Scheduling Plan

EXPECTED BEHAVIOR
-----------------------
Pegging works correctly and there is no negative PAB

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1. (R) Advanced Supply Chain Planner

2. (N) Supply Chain Plan / Names

3. Query the Plan and click launch

4. Wait for plan run to complete

5. (N) Supply Chain Plan / Workbench

6. Observe results in Workbench/Horizontal Plan

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms