Symptoms
On : 12.1.3 version, Memory Based Planner
ACTUAL BEHAVIOR
---------------
There is a work order with a Sugg Due Date of today for 73. On 11/9, there is work order demand for -73. On 11/9, the plan is also suggesting a planned order for 73. Why would the plan cancel the work order and then suggest a new planned order?
- there is no shelf life days
- plan is unconstrained
- work order has a Planning Group and Project Number assigned
- Work order Demand has the same Group and Project Number
- Plan Options Enable Pegging = Yes, Peg Supplies by Demand Priority = Yes, Reservation Level = Planning Group, Hard Pegging Level = Project
EXPECTED BEHAVIOR
-----------------------
The work order should be used rather than suggesting to cancel it only to create a planned order later.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run plan
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |