ASCP Is Suggesting To Cancel Or Reschedule Out Work Order Supply When Supply Can Be Used (Doc ID 2220916.1)

Last updated on SEPTEMBER 19, 2024

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Memory Based Planner

ACTUAL BEHAVIOR
---------------
There is a work order with a Sugg Due Date of today for 73. On 11/9, there is work order demand for -73. On 11/9, the plan is also suggesting a planned order for 73. Why would the plan cancel the work order and then suggest a new planned order?
- there is no shelf life days
- plan is unconstrained
- work order has a Planning Group and Project Number assigned
- Work order Demand has the same Group and Project Number
- Plan Options Enable Pegging = Yes, Peg Supplies by Demand Priority = Yes, Reservation Level = Planning Group, Hard Pegging Level = Project


EXPECTED BEHAVIOR
-----------------------
The work order should be used rather than suggesting to cancel it only to create a planned order later.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run plan


Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution