Risk Register Mapping is Lost When Task ID is Changed (Doc ID 2225528.1)

Last updated on JANUARY 20, 2017

Applies to:

Primavera Risk Analysis - Version 7.8 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
When the task ID is changed in the base plan, task mappings created in the Risk Register are lost.

EXPECTED BEHAVIOR
-----------------------
Expect Risk Register to update the task ID dynamically.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1) Assign a risk to an activity using the Risk Register Quantitative > Pre-Mitigated > Risk View.
2) Save and close the Risk Register.
3) Change the activity ID in the plan.
4) Re-open the Risk Register. The impacted task will still be the previously numbered task.

Cause

Sign In with your My Oracle Support account