PPM Gantt Chart Critical Path Does Not Calculate Weekend Dates For Task Activities (Doc ID 2227253.1)

Last updated on AUGUST 08, 2017

Applies to:

Oracle Agile Product Portfolio Management - Version 9.3.5.0 and later
Information in this document applies to any platform.

Symptoms

PPM Gantt Chart critical path does not calculate weekend dates for task activities.

If a task ends on a Friday and its successor begins on Monday, the Gantt Chart critical path is not calculated and updated.

Steps to Reproduce the Issue
======================
Started off without a weekend task activity:

1. Login to the Web Client as admin
2. Create a New Program; Type: Project; Name: Test Project; Project State: Active; Schedule: Start: 12/06/2016 End: 12/19/2016
3. Click on Schedule Tab; Add a Task a; Schedule Start Date: 12/06/16 Schedule End Date: 12/09/2016
4. Click on Schedule Tab; Add a Task b; Schedule Start Date: 12/12/16 Schedule End Date: 12/12/2016
5. Click on Schedule Tab; Add a Task c; Schedule Start Date: 12/13/16 Schedule End Date: 12/16/2016----> Does not include a weekend
6. Click on Schedule Tab; Add a Task d; Schedule Start Date: 12/19/16 Schedule End Date: 12/19/2016
7. Add Dependency: Predecessor, Type: Finish-to-Start(FS) for Task a--> Task b; Task b--> Task c; Task c-->Task d
8. Click on Gantt Chart button
9. Click on Critical Path button

PPM Gantt Critical Path that does not include a weekend; See below

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms