Running High Volume DRP (DRP-HV) the Plan Fails With Signal 6
(Doc ID 2227313.1)
Last updated on FEBRUARY 26, 2019
Applies to:
Oracle Advanced Supply Chain Planning - Version 12.1.3.9 and laterInformation in this document applies to any platform.
Symptoms
On : 12.1.3.9 version, Memory Based Planner
After increasing the volume being planned in the DRP plan, the plan is failing with a Signal 6.
ERROR
-----------------------
DRP-HV - Db re-connect
SUCCESSFULL after 1 failed connection attempts.
MSONWL64.exe: /<DIR>/mso/src/apscommn/msnmpglobals.cpp:292:
void UpdateDBSequenceNumbers(): Assertion `gl_recom_max_seq_num >
(get_global_transaction_id_start() + 1)' failed.
<MOS_TOP>/bin/MSONWL64.exe
Program was terminated by signal 6
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run DRP plan
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |