The Global Scheduled Services 'Last Run' Date\Time Does Not Update When Configured to Run Manually using the P6Services.jar

(Doc ID 2228351.1)

Last updated on FEBRUARY 16, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.1.0.0 and later
Information in this document applies to any platform.

Symptoms

The Global Scheduled Services 'Last Run' date\time does not update when configured to be run by the P6Services.jar and run manually.

STEPS TO DUPLICATE:
1. Create a new configuration and configure Job Services to run as a separate process using the P6Services.jar file.
2. Locate the Services/Enable All Services setting for the configuration created for user traffic used by P6 (for example, Primavera P6 Configuration). Set the setting to false to disable all services.
3. Login to P6 and select 'Administer' then 'Global Scheduled Services'
4. Right click on any service then choose 'Run Service'.

NOTE: Global Scheduled Services set to run at scheduled intervals updates the 'Last Run' time as expected.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms