In Unifier Budget BPs, Level Of Effort Activities are Not Available in P6 Activity Picker (Doc ID 2230561.1)

Last updated on FEBRUARY 07, 2017

Applies to:

Primavera Unifier - Version 10.1 and later
Primavera Unifier Cloud Service - Version 10.1 and later
Information in this document applies to any platform.

Symptoms

On Primavera Unifier when attempting to create a new record in the following BP's (Initial Budget, Budget Changes or Budget Transfers), and trying to select an activity using the P6 activity picker in the BP, only task dependent activities are listed.
When attempting to create a record in other BP (for example Contract), the Level Of Effort type activities are available and displayed.


Cause