Symptoms

On : 12.2.3 version, Planner workbench

ACTUAL BEHAVIOR
---------------
ASCP did not show forecast on holiday

When a Forecast record is set to a holiday, the information is not visible and planned in ASCP. Data is available in msc_demands but not available in ASCP Plan output.
The forecast value has set on the holiday date.

EXPECTED BEHAVIOR
-----------------------
Forecast is moved in or out to the next available working day.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a Forecast with Qty 100 due on 26-DEC-2016 in JDE Source
2. Update Manufacturing Calendar so the week of 26-DEC-2016 - 30-DEC-2016 is non-working
3. Run Plan
4. Observe results in workbench.



Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution