Milestone End Date Is Different When Displayed on Agile PPM and Openning on XML (Doc ID 2232389.1)

Last updated on FEBRUARY 10, 2017

Applies to:

Oracle Agile Product Portfolio Management - Version 9.3.4.0 and later
Information in this document applies to any platform.

Symptoms

Actual Behavior
Milestone End Date is different when displayed on Agile PPM and openning on XML in Microsoft Project.

Steps
The issue can be reproduced at will with the following steps:

  1. Open a Project in Web Client and go to milestone

    Name : Milestone 1
    Schedule End : 2021/02/21 10:00:00

  2. Action > Microsoft Project > Save as XML - Edit
  3. Open the XML in Microsoft Project 2007
  4. Prompt an Error Message

    Not enough common working time

    A task has been encountered that has task and resource calendars which do not have enough working time in common for work to be performed on the task. The task will be scheduled ignoring the resource calendar. To change how the task is scheduled, try one of the following:

    * Change either the task calendar of the calendar of the resource(s).

    * Select the Scheduling ignores resource calendars check box in the Task Information dialog box to have Project ignore the resource calendar for the task.

  5. On Microsoft Project 2007, show different date as compared with step 1.

    Task name     Duration        Start              Finish                 Predecessors
    -------------------------------------------------------------------------------------------
    Milestone 1    0days            Tue 49-11-16 Tue 49-11-16      200

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms