LEGACY COLLECTIONS RESOURCE REQUIREMENTS ONLY IN THE FIRST DAY OF OPERATIONS (Doc ID 2235296.1)

Last updated on FEBRUARY 18, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

In a VCP 12.2.5.1 Instance:
After running an Unconstrained plan  all of the resource requirements have a start date equal to the first day of the operation.

These are simultaneous resources but we expect them to have different end dates based on setups

Cause