Schedule Duration Calculation Wrong With PPM Calendar (Doc ID 2235950.1)

Last updated on AUGUST 08, 2017

Applies to:

Oracle Agile Product Portfolio Management - Version 9.3.5.0 and later
Information in this document applies to any platform.

Symptoms

On : 9.3.5.0 version, Web client (PPM)

Saturday and Sunday is considered as week end days while calculating schedule duration even if there is change in Calendar week end days (other than Saturday and Sunday)

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a calendar A with all days as working days.
2. Create a template project with some child objects using above calendar.
3. In create Project from template page try to edit the schedule Start/End dates to a date in Saturday/Sunday and Save. System shouldn't throw any error.
4. Also the schedule duration should be correct.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot create a project from a template with Saturday/Sunday as working.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms