Update Baseline Error: "Field "Text" in UDFVALUE May Not Be Set to NULL."

(Doc ID 2239531.1)

Last updated on JUNE 06, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.2.9.0 and later
Information in this document applies to any platform.

Symptoms

When attempting to run Update Baseline, the following error occurs:

ERROR
-----------------------
INFO —-— Updating Activity [A1030 - Name]
INFO —-— Updating Activity Resource/Role Assignments
SEVERE —-- Assignment planned start date cannot be earlier than activity planned start date.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Launch P6 EPPM.
2. Update Baseline.
3. See error that the last job failed.: "SEVERE —-- Assignment planned start date cannot be earlier than activity planned start date."

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot run Update Baseline.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms