Required Capacity Is Showing Inflated Hours Not In Details Of The Plan (Doc ID 2241075.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.5 version, Constrained planning

ACTUAL BEHAVIOR
---------------
Required Capacity in the first bucket is showing inflated hours in the the horizontal view and in supply planner work area for resources. These inflated hours are not shown in the details of the plan.

In the Horizontal Plan, the Required Capacity on 09-JAN-2017 shows 16,046.1, but when you drill into the data, the details only total to 1212.906667.

EXPECTED BEHAVIOR
-----------------------
Expect the details to match the data in the Horizontal Plan.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open the Horizontal Plan and observe the Required Capacity for resource PLYPF10 in the first bucket (09-JAN-2017)
2. Double Click on the number to drill into the details
3. If you export the data to a spreadsheet and sum the values in the Resource Hours/Rate column, you will see that the total is way smaller.



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms