Error: "Task's Completion Date Must Be Earlier Than Parent Task Completion" When Synchronizing Data to EBS From P6 Using Gateway (Doc ID 2243814.1)

Last updated on MARCH 14, 2017

Applies to:

Primavera Gateway - Version 16.1.4.0 and later
Information in this document applies to any platform.

Symptoms

When attempting to synchronize data to EBS from P6 using Gateway, the following error occurs.

Error on TASK :: <tasknumber> :: Project: '<projectname>';Task:<taskname>'
The task's completion date must be earlier than the completion date of the parent task.

The following error can also occur:

Error on TASK :: <tasknumber> :: Project: '<projectname>';Task:<taskname>'
Task start date must not be earlier than Parent Task's start date.

  



Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.