Schedule Comparison's Project Differences Report Reporting Unexpected and Incorrect Results. (Doc ID 2244315.1)

Last updated on APRIL 10, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.1.0.0 and later
Primavera P6 Professional Project Management - Version 16.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 16.1.0.0 and later
Information in this document applies to any platform.

Symptoms

Information in Schedule Comparison Project Differences Report is incorrect and opposite to what the results should be.  For example, when comparing new data added in the Current schedule to the Baseline, the new data added is being reported as deleted from the Baseline.
 
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open Current Project with existing Activities.
2. Next, create a new Baseline Project.
3. Next, add a new Activity in the Current Project.
4. Next, add a new Resource Assignment in the Current Project.
5. Next, add a new Successor Relationship in the Current Project.
6. Next, run Schedule Comparison and select Current Project (left-side) and Baseline (right-side).
7. Result: Comparison output reporting items as being deleted instead of being added.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms