Primavera Gateway Import Extracts Incorrect Values For Start And Finish Dates (Doc ID 2246520.1)

Last updated on JULY 13, 2017

Applies to:

Primavera Gateway - Version 16.1.4.0 and later
Information in this document applies to any platform.

Symptoms

Gateway Import extracts incorrect values for Start and Finish Dates.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. In P6 Export, map Start and Completion Dates to Transaction Start and Finish Date.
2. Run synchronization job, found the extracted "Completion Date" is, for example, 03-Jun-2018, not the completion date of 03-Jun-2017  (Transaction Finish Date)
3. The Source Application formats appears to incorrectly extract the Scheduled Start and End Date values in place of Transaction Start and End Dates for the parent and child tasks from EBS

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms