Check Schedule Report Does Not Display Data Correctly. (Doc ID 2250192.1)

Last updated on APRIL 07, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.2.2.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
In the Check Schedule report, certain fields are not displayed properly. For instance, the Activity ID Field under "Logic - Activities missing predecessors or successors" displays the Activity Description instead of the ID.

EXPECTED BEHAVIOR
-----------------------
Correct records should show in the Check Schedule report.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login to P6 web access, open Project.
2. In the Activities View, choose Actions, Check schedule.
3. Review the Check Schedule report.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot rely on Check Schedule report.

Cause

Sign In with your My Oracle Support account