P6 Integration API Does Not Load Values for Some Spread Periods (Doc ID 2263160.1)

Last updated on MAY 07, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.3.2.0 and later
Information in this document applies to any platform.

Symptoms

When using the Primavera Integration API to load spread periods some periods incorrectly are loaded with a value of zero. 

For example:
When calling project.loadAllActivitiesWithLiveSpread to load activity spreads some periods are showing as 0 even though there is a value.

In the following result list the records with EDT timezone incorrectly display as 0. The values with EST timezone display the correct value.

Activity = A1000 Planned Expense Cost = $0.0 Planned Total Cost = $0.0 AND Spread Period = Sun Jun 01 00:00:00 EDT 2014
Activity = A1000 Planned Expense Cost = $0.0 Planned Total Cost = $0.0 AND Spread Period = Tue Jul 01 00:00:00 EDT 2014
Activity = A1000 Planned Expense Cost = $0.0 Planned Total Cost = $0.0 AND Spread Period = Fri Aug 01 00:00:00 EDT 2014
Activity = A1000 Planned Expense Cost = $0.0 Planned Total Cost = $0.0 AND Spread Period = Mon Sep 01 00:00:00 EDT 2014
Activity = A1000 Planned Expense Cost = $0.0 Planned Total Cost = $0.0 AND Spread Period = Wed Oct 01 00:00:00 EDT 2014
Activity = A1000 Planned Expense Cost = $0.0 Planned Total Cost = $0.0 AND Spread Period = Sat Nov 01 00:00:00 EDT 2014
Activity = A1000 Planned Expense Cost = $2943.543209876543 Planned Total Cost = $10786.135802469136 AND Spread Period = Mon Dec 01 00:00:00 EST 2014
Activity = A1000 Planned Expense Cost = $2943.543209876543 Planned Total Cost = $10786.135802469136 AND Spread Period = Thu Jan 01 00:00:00 EST 2015
Activity = A1000 Planned Expense Cost = $2803.374485596709 Planned Total Cost = $10272.510288065838 AND Spread Period = Sun Feb 01 00:00:00 EST 2015
Activity = A1000 Planned Expense Cost = $3083.711934156374 Planned Total Cost = $11299.761316872435 AND Spread Period = Sun Mar 01 00:00:00 EST 2015
Activity = A1000 Planned Expense Cost = $0.0 Planned Total Cost = $0.0 AND Spread Period = Wed Apr 01 00:00:00 EDT 2015
Activity = A1000 Planned Expense Cost = $0.0 Planned Total Cost = $0.0 AND Spread Period = Fri May 01 00:00:00 EDT 2015

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms