General Info.Calendar Attribute Value Is Removed After Running Update Project Through Web Service (Doc ID 2263244.1)

Last updated on AUGUST 08, 2017

Applies to:

Oracle Agile PLM Framework - Version 9.3.4.0 and later
Information in this document applies to any platform.

Symptoms

Actual Behavior

General Info.Calendar attribute value will be removed after running update project through web service


Expected Behavior

General Info.Calendar attribute value not to be removed after running update project through web service



Steps to Reproduce

The issue can be reproduced at will with the following steps:

  1. Create a Calendar named "7-Day Calendar"
  2. Create a project with all activities Calendar value = "7-Day Calendar"
  3. Run following web service to update activity description to "test"  
  4. All activities' Calendar value will be removed.

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms