UpdateResourceAssignmentPeriodActuals Operation Does not Update the Activity Level Value in Database (PMDB) (Doc ID 2285455.1)

Last updated on JULY 11, 2017

Applies to:

Primavera Web Services - Version 16.2.4.0 and later
Information in this document applies to any platform.

Symptoms

On : P6 Web Services 16.2.4.0 version, Business Objects

When attempting to call the UpdateResourceAssignmentPeriodActuals Operation, the value is updated at the Assignment level but not the Activity level.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:

Due to this issue, users cannot update Actual Units and Cost on Financial Periods at the Activity level if there are Assignments. If there is a call to the UpdateActivityPeriodActuals Operation the following but correct business rule error is thrown:

Errors located: ActualLaborUnits: ActualLaborUnits may only be set on the associated labor resource assignment's period actual business object. ActualLaborCost: ActualLaborCost may only be set on the associated labor resource assignment's period actual business object.

EXPECTED BEHAVIOR
-----------------------
Just like with P6 EPPM, it is expected that an update as the Assignment level triggers the same update to the Activity level.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms