When Running a Primavera Gateway Synchronization to Copy a Calendar the Error"Invalid Calendar Type: Project" Occurs (Doc ID 2286091.1)

Last updated on AUGUST 07, 2017

Applies to:

Primavera Gateway - Version 16.2.4.0 to 17.7 [Release 16.2 to 17.7]
Information in this document applies to any platform.

Symptoms

When attempting to run a synchronization that copies a calendar from one project to a new project in the same P6 database, it was noticed that when the activities use a project specific calendar, the copy fails with the error

Invalid calendar type: Project


STEPS
--------

  1. Create a synchronization in Gateway that copies a project and baseline from "XXXX" to "XXXX Copy", within the same P6 database, using groovy scripts in the field mapping template to rename the Project ID.
  2. Add the Calendars object to the business flow.
  3. Alter the field mapping so that the Project ID for the destination is "XXXX Copy", so that the calendar is copied from project "XXXX" to "XXXX Copy".

Changes

 

Cause

Sign In with your My Oracle Support account