Activity Type Changes To Task Dependent After Running EBS To P6 Gateway Synchronization

(Doc ID 2288300.1)

Last updated on JULY 19, 2017

Applies to:

Primavera Gateway - Version and later
Information in this document applies to any platform.


On : version, Providers

When synchronizing data to P6 that was previously synchronized to eBS, all activity types change to task dependent.

For the activity type to remain unchanged between systems.

The issue can be reproduced at will with the following steps:

1. Create 4 activities each with different types: Task Dependent, Start Milestone, Finish Milestone, and WBS Summary.
2. Synchronize data from P6 to eBS using Gateway.
3. Synchronize data from eBS to P6 using Gateway.
4. Note all activities are now Task Dependent.

The issue has the following business impact:

Due to this issue, activity type is always lost when synchronizing activities from EBS to P6.


Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms