I Cannot Find Manufacturing And Distribution Manager Responsibility On ASCP (Doc ID 2291482.1)

Last updated on JULY 28, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Oracle Materials Requirement Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, User Interface in TEST

Users have a Legacy collections instance. They are trying to setup and run an MRP plan using the old MRP product (ie not ASCP). However they run into the following error when using Material Planner Responsibility / MRP / Launch

ERROR
======
No Organizations are currently defined

When they try to go to Inventory / Setup> Organizations>Organization Access> Add new records in this list for> Save - this Errors

ERROR
======
FRM-41830 - List of Values contains no entries

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Navigate Material Planner / MRP / Launch - see no organizations error
2. Inventory / Setup> Organizations>Organization Access> Add new records in this list for> Save - this Errors FRM-41830

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms