Symptoms

On : 12.2.4 version, Memory Based Planner in All instances:

Users are on 12.2.4 and have applied VCP Cum Patch 12.2.4.1 - 19549533

Users are comparing old MRP/SCP output for forecast data vs ASCP plan output for same. They are seeing more forecast qty's in some cases for the following item/org combination in ASCP vs SCP

Item = Item1
Org = APS:M1

In SCP they see total forecast qty = 725. In ASCP for the same item/org they see total forecast qty = 844


EXPECTED BEHAVIOR
-----------------------
Expect the forecast qty's to be the same in ASCP and SCP

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run old MRP/SCP plan with demand schedule including forecast and note forecast qty's for item/org combination
2. Run data collections and ASCP plan with forecast demand schedule and note forecast qty's for item/org combination
3. See discrepancies between the two plan outputs in regards to forecast qty's

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.