It Takes 15 - 30 Seconds to Delete 6 WBS Nodes With 30 - 60 Activities

(Doc ID 2294733.1)

Last updated on AUGUST 21, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 16.1.4.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

It takes about 20 seconds to delete 6 WBS nodes with 30 activities.

EXPECTED BEHAVIOR

It is expected to complete in short time.

STEPS


The issue can be reproduced at will with the following steps:
1. Login to P6 Pro For EPPM.
2. Open project and switch to WBS view.
3. Select 5-6 WBS nodes with 30 - 60 activities and delete the same.

BUSINESS IMPACT

The issue has the following business impact:
Due to this issue, users cannot delete WBS nodes quickly.

Cause