My Oracle Support Banner

When Using MRP Planned Safety Stock Method, Can It Be Setup To Only Take Into Account Independent Demand And Not Dependent Demand In Its Calculation? (Doc ID 2296438.1)

Last updated on AUGUST 11, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.4 and later
Information in this document applies to any platform.

Goal

On : 12.2.4 version, Memory Based Planner in All instances

Users would like to know if safety stock can be setup to only calculate based on Independent demand like forecast and sales orders and ignore any dependent demand. Example:

ItemA has safety stock setup
Method = MRP Planned
Bucket Days = 10
Percent = 1000

Demand
=======
Sales order demand due day 5 qty = 10
Forecast demand due day 6 qty = 10
dependent demand due day 5 qty = 5

Users want the safety stock calculation to only use the qty = 10 sales order demand and qty = 10 forecast demand and ignore the dependent demand qty = 5. Is this possible?
 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.