Schedule Options are Changed When Importing an XER to a SQLite Database. (Doc ID 2299512.1)

Last updated on SEPTEMBER 17, 2017

Applies to:

Primavera P6 Professional Project Management - Version 15.2.0.0 and later
Information in this document applies to any platform.

Symptoms

ISSUE DESCRIPTION:
When exporting the Project, the schedule option chosen is "Progress Override". However, when importing it to the other system with database type SQLite, the schedule option changed to "Retained Logic".

REPRODUCE STEP:
1. Schedule a Project with option "Progress Override".
2. Export the Project as XER.
3. Check the XER and make sure you can find the following settings:
%T SCHEDOPTIONS
%F sched_retained_logic sched_progress_override
%R N Y
4. Import it to another system with SQLite.
5. Close all Projects and only open the newly imported one (This is to make sure the schedule option is not affected by any other Projects).
6. Press "F9" for Scheduling and go to "Options".
7. Check what's the setting for "When scheduling progressed activities use"...

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms