EBS: PS: PS Publish Changes Component Supply Type (Doc ID 2300663.1)

Last updated on AUGUST 24, 2017

Applies to:

Oracle Production Scheduling - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

Product Build Number: 12.2.5.C612

PS is altering the supply type for components during the PS publish. The Bill of materials on the Job is set to operation pull and after the publish it is
assembly pull. We looked at the WIP MASS LOAD interface file and it specified this change.

WORKAROUNDS
===========
manual changes.

Cause