Schedule Options Are Not Retained When Copying/Pasting a Project in P6 Professional Client (EPPM Using Job Services)

(Doc ID 2307718.1)

Last updated on NOVEMBER 07, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.2.14.0 to 17.7 [Release 15.2 to 17.7]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.2.14.0 to 17.6 [Release 15.2 to 17.6]
Primavera P6 Professional Project Management - Version 15.2.14.0 to 17.7 [Release 15.2 to 17.7]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR:
Schedule Options are not retained when copying and pasting a Project via EPPM Job Services.

EXPECTED BEHAVIOR:
Schedule Options are retained when copying and pasting a Project.

STEPS:
The issue can be reproduced at will with the following steps:

  1. Create a Project and customize the Schedule Options.
  2. Copy/paste the Project.
  3. Open the new Project.
  4. View Schedule Options (set to default settings).

BUSINESS IMPACT:
The issue has the following business impact:
Due to this issue, users need to refer back to the original Project to set the Schedule Options manually.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms