Cannot Find Option Send to Schedule Sheet in Standard View

(Doc ID 2309691.1)

Last updated on SEPTEMBER 27, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.1.0.0 and later
Primavera Unifier - Version 10.1 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
Not able to see Send to Schedule Sheet after integration with Unifier.

EXPECTED BEHAVIOR
-----------------------
Be able to see Send to Schedule Sheet after integration with Unifier.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login to P6 EPPM.
2. Navigate to Administer > Application Settings > General..
3. In General section, provided Primavera Unifier URL, Company Short name and Authentication code.
4. Navigate to Project tab and select project to link to Unifier.
5. Right click on project and select "Set Project Preferences"
6. Click on Integration tab and select Unifier.
7. Check the option "Link project to a Primavera Unifier project"
8. Select Unifier project name, Schedule sheet and data mapping.
9. Open P6 project and navigate to Activities tab in Standard View, click on Action and exchange data.

After performing this steps, cannot find option to send Schedule Sheet to Primavera Unifier.

BUSINESS IMPACT
-----------------------
Due to this issue, users cannot see option to Send to Schedule Sheet.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms