My Oracle Support Banner

Change of "MRP: Calculate Supply & Demand" Profile Option Is Impacting Scheduling and ATP Inquiry (Doc ID 2310491.1)

Last updated on AUGUST 31, 2020

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.4 version, Oracle Global ATP Server

ACTUAL BEHAVIOR
---------------
When doing ATP Inquiry

A. If "MRP: Calculate supply demand" set to Yes, then Request Date quantity is 4.
B. If "MRP: Calculate supply demand" set to No, then Request Date quantity is 0.

EXPECTED BEHAVIOR
-----------------------
ATP Inquiry should provide the same result, irrespective of profile value.

Profile MRP: Calculate supply demand should not impact the results.

Happens when MSC: Enable summary ATP profile  - Yes

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. ATP Inquiry


Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.