Gantt Chart Not Showing If There Is No Activity Today

(Doc ID 2316021.1)

Last updated on OCTOBER 10, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3.9.2 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3.9.2 version, User Interface

ACTUAL BEHAVIOR
---------------
Gantt chart not showing if there is no activity today

Resource Gantt chart is not showing anything if there is no orders or resource activities for today. Even though there are activities in the future, still it is not showing anything.
if that resource is selected with another resource which has today's activities, then it shows both.

EXPECTED BEHAVIOR
-----------------------
Gantt Chart will show.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Select two resources that do not have any scheduled activity today, but future activity and show Gantt Chart
2. Gantt Chart opens with a blank window
3. Select the same two resources and an additional one that has activity for today and the future and show the Gantt Chart
4. Gantt Chart opens with information for all three resources.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms