What Is the Correct Behavior for Copy/Paste Activity Into the Same Project in the Web?

(Doc ID 2319317.1)

Last updated on NOVEMBER 01, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 16.2.9.0 and later
Information in this document applies to any platform.

Symptoms

Copy an Activity into the same Project and Risk Assignments and Risk User Defined Fields (UDDFs) paste with the new Activity in P6 Web.

P6 Web Online Help indicates that Risk Assignments do not copy with an Activity.

P6 Web Online Help:
Copying and Pasting Activities
When you copy an activity, the following data items are not copied: Issues, Assignment UDF values, Expense UDF values, Step UDF values, Activity Feedback, Risk Assignments, and Status Update History (from Team Member interfaces only).

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms