Goal

It's our understanding that 'Resource (used/total)' shown at the bottom of the window in Planner signifies the number of vans available for a depot.  In Planner for depot 1234 it is showing 'Resources (used/total): 1/5'.  For this depot there is only 1 driver available. The same behavior is observed for other depots.  How are these values determined?

Solution