PS: Incorrect Work Order Links in Production Pegging View

(Doc ID 2323447.1)

Last updated on OCTOBER 31, 2017

Applies to:

Oracle Production Scheduling - Version 12.2.6 to 12.2.6 [Release 12.2]
Information in this document applies to any platform.

Symptoms

On : 12.2.6 version, Planning Engine

ACTUAL BEHAVIOR
---------------
Work Order links in Production Pegging View connect Request Date (instead of Completion or Available Date) of upstream work order with Start Date of downstream work order